Project status report template

A one-page status report for a project's sponsor or steering group: the overall status in one word, red, amber or green for each area, milestones against plan, the risks, and the decisions you need this week.

Use this template needs the free Obsidian plugin; it makes a new note from the outline.

Example · Kestrel · Scanner rollout status

Scanner rollout, status at week 6 of 14.
Overall amber: on budget, two weeks late at Reno.

Weekly status report to the steering group, October 9, 2026. Kestrel Logistics is replacing paper pick lists with handheld scanners in its four warehouses. Project lead: Maya Okafor. Next report: October 16.

01Status at a glancegreen on track, amber at risk, red off track
Amber
overall, green last week
2 of 4
warehouses live
$412K
spent of a $680K budget
Nov 20
last go-live, the plan was Nov 6
Area
Status
Why
Scope
yes
No change since kickoff: four sites, pick and pack only
Schedule
at risk
Reno's Wi-Fi survey found dead zones in aisles 30–44; two weeks to fix
Budget
yes
61% spent at 43% of the timeline, as planned: hardware was paid up front
People
yes
212 of 340 pickers trained; the rest are booked by October 30
Vendor
no
The last 90 scanners are held at customs; no release date yet

What changed since last week Schedule went from green to amber. Reno needs eight more Wi-Fi access points before scanners work in every aisle. The installer starts October 19.

02Milestonesplan against forecast
Scanner rollout
07.0914.0921.0928.0905.1012.1019.1026.1002.1109.1116.11
Sites
Columbus live
Memphis live
Reno Wi-Fi fix
Reno live
Dallas live
Project
Picker training
All four sites live
Milestone
Plan
Forecast
On date
Columbus live
Sep 19
done Sep 18
yes
Memphis live
Oct 3
done Oct 2
yes
Reno live
Oct 23
Nov 13
no
Dallas live
Nov 6
Nov 13
at risk
Paper pick lists retired
Nov 13
Nov 20
at risk

Picks per hour, paper against scanners

Picks per picker-hour: paper (bars), scanners (line)
Picks per hour
050100150
96131
Columbus
102124
Memphis
9191
Reno
9999
Dallas

Reading it: the two live sites pick 22–36% faster with scanners. Reno and Dallas are still on paper, so their line meets the bar.

03Risks and issueswhat could hurt the date, and what already does
Risk or issue
Impact
Owner
Contained
Issue: 90 scanners held at customs
high
Dev, procurement
no
Issue: Reno Wi-Fi dead zones
high
Ana, IT
yes, but late
Risk: Dallas peak season starts Nov 16
high
Maya
yes, but tight
Risk: night shift trained last
medium
Leo, operations
yes
Risk: label printer driver on old Windows
low
Ana, IT
yes
04Decisions neededfrom the steering group by October 14

The question If the held scanners are not released by October 20, Dallas cannot go live before its peak season. Moving it to January avoids changing a warehouse mid-peak but keeps paper there for two more months.

A · Lease 90 scanners$18K for three months, from the same vendor. Dallas goes live November 13 as planned.
B · Move Dallas to JanuaryNo extra cost. Dallas stays on paper through peak season; the project ends January 22.
C · Split DallasDay shift on scanners now, night shift in January. Cheaper than A, but two ways of working in one building.

Our recommendation: A. The $18K comes out of the $40K contingency, and faster picking at Dallas pays it back in about five weeks.

Next week

  1. Reno. The Wi-Fi installer on site from October 19; a survey of every aisle after.
  2. Training. The last 128 pickers, night shift first.
  3. Customs. Daily calls with the broker until the 90 scanners are released.

A project status report tells the people who fund and steer a project whether it will land on time and on budget, and what they need to do about it. It is read by a sponsor, a steering group or a client, usually in the five minutes before a meeting. They want the answer first and the detail second, and they want to see the same layout every week so a change jumps out.

This template uses the common RAG format: red, amber or green for each area, an overall status, milestones, a risk and issue log, and a short list of decisions. The example above is week 6 of a fictional rollout of handheld scanners in four warehouses: on budget, two weeks late at one site, with one decision for the steering group.

What goes in each section

The headline

The overall status in one word and the reason in one line: "Overall amber: on budget, two weeks late at Reno." Under it, the date, who the report is for, the project lead and the date of the next report. Mistake to avoid: a headline that only says "Week 6 status". The reader should know the answer without scrolling.

01 · Status at a glance

Four big numbers (overall status, progress, budget spent, the forecast end date), then a table with one row per area: scope, schedule, budget, people, vendors. Each row gets a coloured status and one line of why. Below it, say what changed since the last report. Mistake to avoid: statuses with no reason. "Amber" alone starts a meeting; "amber, Wi-Fi dead zones in aisles 30 to 44, two weeks to fix" ends one.

02 · Milestones

A timeline with finished, current and late work, and a table of each milestone's planned date against its forecast. If the project has a number that shows it working, add a small chart: the example compares picks per hour on paper and on scanners per warehouse. Mistake to avoid: moving the plan dates quietly. Keep the original plan from the project brief and show the forecast next to it.

03 · Risks and issues

One table for both. An issue has already happened; a risk might. Give each an impact, an owner and whether it is contained. Five rows is plenty; keep the full register elsewhere if you need one. Mistake to avoid: a risk with no owner. Nobody acts on it until it becomes an issue.

04 · Decisions needed

The question, the options with their cost and effect on the date, and your recommendation. Then the plan for next week in three lines. Mistake to avoid: asking for a decision without a deadline. Say by when, and what happens if nobody decides.

How often, and how long

Weekly is the default; every two weeks suits long projects with slow change. For a team with ongoing work and no end date, a weekly update is lighter. It should take 20 to 30 minutes to update if you keep it as one living page and change only what moved. Readers should get through it in under five minutes. If yours runs longer, move detail to linked pages and keep the status, the milestones and the decisions on top.

How to use this template

Each week, duplicate last week's note or edit the same one. The milestone dates and the gantt bars are edited right on the page, so the timeline stays current without redrawing it.

Where myone.page helps

Status reports go stale when they live in a slide deck that one person updates. Shared as a link, the sponsor reads the same page each week, and workstream leads can edit their own rows in the browser without Obsidian; their edits come back into your note. If your company already runs projects in Jira, Asana or Smartsheet and the sponsor reads dashboards there, a status field in that tool may be enough. Use this page when you need the story and the decision, not just the bars.

Questions

What does RAG status mean?

Red, amber, green. Green is on track, amber is at risk but recoverable by the team, red is off track and needs help or a decision from above. Write down what each colour means for your project at kickoff, so amber means the same thing every week.

How often should I send a project status report?

Weekly for most projects, every two weeks for long ones with little change. Send it on the same day each time, and send an extra one the day a status turns red rather than waiting for the next report.

What is the difference between a status report and a status update?

Mostly length and audience. A status report goes to a sponsor or steering group and covers schedule, budget, risks and decisions. A status update is often shorter and goes to the team; the weekly update template is built for that.

Should the overall status be the worst of the areas?

Not automatically. Use judgement and say why: one amber area the team can fix this week can leave the project green overall. But never report green overall with a red area; that is the report readers stop trusting.